Data centres have been Johor’s favourite talking point for two years, and plenty of summary tables are doing the rounds. The trouble is that those tables add up project investments, construction costs, green financing facilities and land purchase prices as if they were the same kind of money. They are not, and the total you get from adding them means nothing. This page sets out what each number actually counts.
In one line: Johor has approved 42 data centre projects worth RM164.45 billion (Menteri Besar Onn Hafiz Ghazi, Q2 2025 figures). Nationally, the Data Centre Task Force has approved 27 projects with an estimated value of RM225.97 billion, of which 16 are in Johor (July 2026). A Johor state exco member said on 25 October 2026 that, counted by land plot, the state has approved 65. Three different counting bases — do not mix them.
When you look at any data centre table, read the “type of amount” column first. The same RM2 billion can mean very different things:
| Type | What it means | Does it actually get spent in Johor |
|---|---|---|
| Project investment | What the operator says it will put into this project, usually over several years | Yes, but in phases and often conditionally |
| Construction cost | The estimated cost of building the facilities | Yes, but it excludes land and much else |
| Financing facility | The ceiling a bank has granted, which can include refinancing existing debt | Not necessarily new investment at all |
| Land purchase price | What was paid to the landowner, once | Yes, but it is a small slice of the whole project |
What this table covers: the state has approved 42 projects, but details were never published for most of them. The 11 below are the ones with enough public information to verify — the published portion, not all 42.
Every entry below was traced back to a company release, a Bursa Malaysia filing, MIDA or a state government statement. Where nothing was published, this page says so rather than filling in an estimate.
| Project | Location | Land | Amount | What that money is |
|---|---|---|---|---|
| YTL Green Data Center Park | Kulai | 275 acres (YTL’s own site; news reports say 111 hectares) | RM15 billion | Investment the state government expects the park to attract over ten years — not YTL’s capex. YTL Power’s own phase 1 is RM1.5b; Sea a further RM1.5b |
| AirTrunk JHB1 + JHB2 | JHB2 in Iskandar Puteri; JHB1 stated only as Johor Bahru | JHB1 10.3 ha (25.5 acres); JHB2 not published | RM9.7 billion | Construction cost for the two facilities combined. Over 420MW of IT load together |
| DayOne (NTP + KTP) | Nusajaya Tech Park + Kempas Tech Park | Not published | RM15 billion | Green financing facility (RM7.5b Islamic + US$1.7b offshore), for refinancing and capex — not new investment |
| DayOne Gerbang Nusajaya | Mukim Tanjung Kupang, Iskandar Puteri | 26.42 ha (about 65.28 acres) | RM398.11 million | Land purchase price; seller Paragon Globe, shareholder approval 28 October 2026 |
| Princeton Digital Group JH1 | Sedenak Tech Park | 31 acres | RM2 billion | Project investment. A 150MW campus, phase 1 of 60MW |
| Bridge Data Centres MY06 | Kidex Sedenak | About 40 acres | RM2.5 billion | Project investment, over five years. 100MW IT load |
| Vantage (formerly Yondr) JHB1 | Sedenak Tech Park | “Nearly 73 acres” per the operator | Not published | No project cost published. The US$1.6b figure in circulation is equity into Vantage’s APAC platform from GIC and ADIA, not a Johor project cost |
| Equinix JH1 | Nusajaya Tech Park | Not published | US$40 million (about RM188 million) | Initial investment. A 1,800 sqm two-storey facility, up to 500 cabinets |
| Microsoft (two deals) | Kulai + Tebrau | 123.141 acres + 138.532 acres | RM402.3m + RM693.96m | Two land purchase prices, about RM1.096 billion over 261.7 acres. At the time of the Kulai deal the park was still called Eco Business Park VI |
| Digital Edge | Kota Tinggi (Bandar Cemerlang industrial park) | 49.72 acres freehold | RM346.53 million (RM160 psf) | Land purchase price; seller Crescendo, filing 9 April 2026 |
| KNBDC Malaysia Five | QUANTUM Edge, Kulai | 49.588 acres (two parcels) | RM280.8 million | Land purchase price; seller EcoWorld, filing 24 April 2026, the final QUANTUM Edge parcels |
One: YTL’s RM15 billion is not YTL’s money. At the August 2022 groundbreaking the Menteri Besar said that was the investment the state expects the park to attract over ten years. YTL Power’s own phase 1 commitment is RM1.5 billion.
Two: Digital Edge’s land is in Kota Tinggi, not Ulu Tiram. The Bursa filing says Bandar Cemerlang industrial park, Mukim and District of Kota Tinggi. The Ulu Tiram facility people are thinking of is a Bridge Data Centres reclaimed-water plant — a different company and a different thing.
Three: Microsoft bought two plots in Johor, not one. Besides the 123.141 acres in Kulai for RM402.3 million, it bought 138.532 acres at Eco Business Park I in Tebrau for RM693.96 million in February 2025. Count only the first and you leave out more than half.
For a buyer this matters more than the investment totals, because it governs how much more can be approved.
No blanket moratorium has been gazetted. The approach is case-by-case tightening, not a freeze.
So how should a buyer use these numbers: data centres take a lot of land and a lot of power, but employ relatively few people — RM225.97 billion nationally against 4,053 jobs. What actually underpins housing demand is the JETP pipeline: 83 projects and 200,000 jobs (see Johor: 83 projects, RM167.4 billion). Data centres are one piece of that board, not the whole of it. When you look at a project, do not accept a premium just because “there is a data centre nearby” — look at the actual employment density of that area and the drive to the checkpoint and the city.
These districts are a different proposition from the checkpoint corridor — different distances, different buyers, different tenants. The Johor Bahru project list is ranked by distance to the checkpoint, and every page carries the declared price range, the title, the unit count and the advertising permit number.
Want to know how far the project you are looking at sits from each industrial cluster, and who actually rents in that area? Send me the project name and I will give you the real numbers.
Check this project’s location for me
No phone number needed — just WhatsApp
It depends on the counting basis. The Menteri Besar’s Q2 2025 figure was 42 approved projects worth RM164.45 billion. A state exco member said on 25 October 2026 that, counted by land plot, it is 65. Of the 27 projects approved by the national Data Centre Task Force, 16 are in Johor. The state also says 21 are currently operating. These are different methods, not contradictions.
The state is already tightening. Since late 2025 it has not approved less efficient Tier 1 and Tier 2 facilities; in March 2026 the Menteri Besar said water-intensive projects will not be approved, with households first; SPAN requires reclaimed water for cooling as the first option. On power, TNB has signed 8.3GW of supply agreements with 68% of that in Johor, all take-or-pay, and the state plans about 5GW more solar by 2030–2031. Johor and the federal government are also spending RM5 billion on three reservoirs and three treatment plants.
Do not accept a premium simply because there is a data centre nearby. They occupy a lot of land and draw a lot of power, but employ relatively few people — 4,053 jobs across the 27 nationally approved projects. Housing demand comes from labour-intensive industry and the JS-SEZ roles. What to look at instead is the employment density of the area, the drive to the checkpoint and the city, and who actually rents there — all of which you can check on the project list and the area pages.
Mainly two clusters: Nusajaya / Iskandar Puteri and Sedenak / Kulai, with further projects in Kempas, Tebrau and, most recently, Kota Tinggi. All of them sit some distance from the Johor Bahru checkpoint, and follow a different logic from the checkpoint-corridor residential market.
Because they add together four different kinds of money: project investment, construction cost, financing facility and land purchase price. A financing facility can include refinancing existing debt, and a land price is only a small slice of a project. Before comparing two tables, check that the amount-type column lines up.
This page is general information and commentary. It is not investment advice and contains no return projections. Every amount is classified according to how the official source described it, and anything unpublished is stated as such. Investment figures, land areas and progress are subject to later official announcements. Last verified: 29 October 2026.
Questions about anything in this article? Message me and I'll answer directly.